quarta-feira, 12 de dezembro de 2012

7 Habits of Highly Effective Microsoft Project Users - Be Proactive


Be Proactive

Perhaps the most critical aspect of being a project manager/scheduler is to take complete ownership of the schedule.  As project managers, we can’t accept ‘hard-coded’ dates given to us by the sponsor, team members or other stakeholders.  In organizations with limited resources, in particular, it’s critical that we change the conversation to the following:

Ask Team Members for a commitment to the ‘effort’ (work) estimate, not delivery dates or durations.  As project managers, we need to understand the true effort of the work to be performed.
Example: Your developer tells you that she can have the updated prototype ready in 5 weeks, but when asked to clarify the effort involved, we discover that it’s only 40 hours of effort.  The 5 weeks duration estimate was based on a week of vacation time (already accounted for in the project calendar), known commitments on other projects and various support activities.
Ask Resource Managers for a commitment to allocation of their resources on your project.  As project managers, we need to understand what resources are available to us and at what percentage.
Example: The developer had previously estimated the scope of work to be 40 hours of effort (work).  The resource manager now allocates this individual to your project at 50%.




As Project Managers, we should only ever commit to dates based on effort estimates received from team members and the commitment to allocation from resource managers.   So, armed with the effort estimate of 40 hours from the team member and 50% allocation from the resource manager, we can now calculate the true duration (2 weeks) of the task and see the resulting schedule impact based on the complete dependency network and the supporting calendars.  If the result is a missed deadline then we can have an intelligent conversation with our sponsor about either reducing scope or allocating more of the resource’s time to the project. While the above example was very simple, the complexity on projects is typically much greater and as such, Microsoft Project takes care of more advanced calculations and factors in non-working time, lead/lag and dependencies as well.

Going forward, any dates given to you by your sponsor or anyone else on the project should be entered as a ‘deadline’ only, never as a ‘start’ or ‘finish’ date as that would hardcode your schedule and take ownership away from you.

You are the ‘programmer’, ‘author’ and owner of your schedule, so don’t make excuses or live your schedule by someone else’s script.

Nenhum comentário:

Postar um comentário